Contract No: HK/2009/05 Wanchai Development Phase II and Sampling, Field Measurement and Testing Work (Stage
1) Environmental
Permit no. EP-364/2009/A, Further Evironmental permit nos. fep-01/364/2009,
fep-02/364/2009, FEP-03/364/2009, FEP-05/364/2009/A, FEp-06/364/2009/a
and FEP-07/364/2009/A Monthly Environmental Monitoring
& Audit Report
- December 2011 -
|
CLIENTS: |
|
Civil Engineering and
Development Department and Highways Department |
Lam Geotechnics Limited 11/F Centre Point Wanchai, H.K. Telephone: (852) 2882-3939 Facsimile: (852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
|
|
|
|
|
Certified
by: |
|
Raymond Dai Environmental Team
Leader |
|
DATE: |
|
18 January 2012 |
2.2 Scope
of the Project and Site Description
2.3 Division
of the Project Responsibility
2.4 Project
Organization and Contact Personnel
3. status of regulatory compliance
3.1 Status
of Environmental Licensing and Permitting under the Project
5.2 Real Time Noise Monitoring Results
6.2 Real Time Noise Monitoring
6.4 Review
of the Reasons for and the Implications of Non-compliance
6.5 Summary
of action taken in the event of and follow-up on non-compliance
7. Cumulative Construction Impact due to the
Concurrent Projects
9. Complaints,
Notification of Summons and Prosecution
lIST OF TABLES
Table 2.1 Schedule
2 Designated Projects under this Project
Table 2.2 Details of Individual Contracts under the Project
Table 2.3 Contact Details of Key Personnel
Table 3.2 Cumulative Summary of Valid Licences and Permits under Contract no.
HY/2009/17
Table 3.3 Summary of submission status under FEP-03/364/2009
Table 3.4 Cumulative Summary of Valid Licences and Permits under Contract no.
HK/2009/01
Table 3.5 Summary of submission status under FEP-02/364/2009
Table 3.6 Cumulative Summary of Valid Licences and Permits under Contract no.
HK/2009/02
Table 3.7 Summary of submission status under FEP-01/364/2009
Table 3.8 Cumulative Summary of Valid Licences and Permits under Contract no.
HY/2009/18
Table 3.9 Summary of submission status under FEP-05/364/2009/A
Table 3.10 Cumulative Summary of Valid Licences and Permits under Contract no.
HY/2009/15
Table 3.11 Summary of submission status under FEP-06/364/2009/A
Table 3.12 Cumulative Summary of Valid Licences and Permits under Contract no.
HY/2009/19
Table 3.13 Summary of submission status under FEP-07/364/2009/A
Table 4.1 Noise Monitoring Stations
Table 4.2 Real Time Noise Monitoring Stations
Table 4.3 Air Monitoring Stations
Table 5.1 Noise Monitoring Stations for Contract no. HY/2009/17
Table 5.2 Noise Monitoring Stations for Contract no. HY/2009/18
Table 5.3 Noise Monitoring Station for Contract no HK/2009/01 and HK/2009/02
Table 5.4 Noise Monitoring Stations for Contract no. HY/2009/15
Table 5.5 Noise Monitoring Stations for Contract no. HY/2009/19
Table 5.6 Real Time Noise Monitoring Stations for Contract no. HY/2009/17
Table 5.7 Real Time Noise Monitoring Stations for Contract no. HY/2009/19
Table 5.8 Air Monitoring Station for Contract no. HY/2009/17
Table 5.9 Air Monitoring Stations for Contract no. HY/2009/18
Table 5.10 Air Monitoring Station for Contract no. HK/2009/01
Table 5.11 Air Monitoring Station for Contract no. HK/2009/02
Table 5.12 Air Monitoring Station for Contract no. HY/2009/15
Table 5.13 Air Monitoring Stations for Contract no. HY/2009/19
Table 5.14 Details of Waste Disposal for Contract no. HY/2009/17
Table 5.15 Details of Waste Disposal for Contract no. HK/2009/01
Table 5.16 Details of Waste Disposal for Contract no. HK/2009/02
Table 5.17 Details of Waste Disposal for Contract no. HY/2009/18
Table 5.18 Details of Waste Disposal for Contract no. HY/2009/15
Table 5.19 Details of Waste Disposal for Contract no. HY/2009/19
Table 8.1 Summary of Environmental Inspections for Contract no. HY/2009/15
Table 8.2 Summary of Environmental Inspections for Contract no. HY/2009/18
Table 8.3 Summary of Environmental Inspections for Contract no. HY/2009/19
Table 8.4 Summary of Environmental Inspections for Contract no. HK/2009/01
Table 8.5 Summary of Environmental Inspections for Contract no. HK/2009/02
Table 9.1 Cumulative Statistics on Complaints
Table 9.2 Cumulative Statistics on Successful Prosecutions
lIST OF
FIGUREs
Figure
2.1 Project
Layout
Figure
2.2 Project Organization Chart
Figure 4.1 Locations
of Environmental Monitoring Stations
lIST OF APPENDIces
Appendix 3.1 Environmental
Mitigation Implementation Schedule
Appendix 4.1 Action and
Limit Level
Appendix
4.2 Copies of Calibration
Certificates
Appendix
5.1 Monitoring Schedule for Reporting
Month and Coming month
Appendix 5.2 Noise Monitoring Results and Graphical
Presentations
Appendix 5.3 Air Quality Monitoring Results and Graphical
Presentations
Appendix
5.4 Real-time Noise Monitoring Results and Graphical
Presentations
Appendix 6.1 Event
Action Plans
Appendix 6.2 Notification of Exceedance
Appendix
9.1 Complaint Log
Appendix 10.1 Construction
Programme of Individual Contracts
Contract no. HY/2009/17 - Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot
- Advanced piling works under FEP-03/364/2009
·
ELS works
for basement construction for pile cap construction.
Contract
no. HY/2009/18 - Central - Wan Chai Bypass (CWB) - Central Interchange under FEP-05/364/2009/A
·
Instrumentation
works for Manholes and Intake Culvert Survey
·
Excavation
of trial pit
·
Drainage
work
·
Site
investigation and pre-drilling works
·
Diaphragm
wall construction
·
Hoarding
erection
·
Roadworks
·
Grout
curtain
·
Tree
purning
Contract no. HK/2009/01 - Wan Chai Development Phase II - Central - Wan
Chai Bypass at
·
Diaphragm
wall construction works for CWB (stage 1).
·
Pre-drilling
works for CWB (stage 2).
·
Pre-bored
H pilling works for CWB (stage 1).
Contract no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
·
Tunnel
bored pile works at WCR1 area
·
Toe grout
at WCR1 area.
·
Shear pin
at WCR1 area.
·
Pumping
test at WCR1 area.
·
King Post
at WCR1 area.
·
West
bulkhead capping beam.
·
Steel
deck support for cooling main.
·
Working
deck B at WCR1.
·
Deep
excavation of CWB at the eastern area of working deck B.
Contract
no. HY/2009/15 - Central-Wanchai Bypass – Tunnel (
·
Seawall
block construction, reclamation work and diaphragm wall construction
preparation works at TS4
·
Diaphragm
wall construction at TS1 and TPCWAE
·
Night
time protection works at CHT
·
Construction
of dewatering well at
·
Precautionary
works at Abutment A
Contract
no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and
Island Eastern Corridor Link under
FEP-07/364/2009/A
·
Preparation
works and concreting of marine piles
·
Fabrication
of bored piling platform
·
Bored
piling
·
Ground
contamination assessment
·
D-wall Construction
·
Sheet
piling for Box Culvert T
·
Construction
works for Box Culvert T
Noise Monitoring
Air Monitoring
Complaints, Notifications of Summons and Successful Prosecutions
Site Inspections and Audit
Contract no. HY/2009/17 –
Central – Wan Chai Bypass (CWB) at FEHD Whitfield Depot – Advanced piling works
under FEP-03/364/2009
·
ELS works
for basement construction for pile cap construction.
Contract no. HY/2009/18 – Central – Wan Chai
Bypass (CWB) – Central Interchange under FEP-05/364/2009/A
·
Instrumentation
works for Manholes and Intake Culvert Survey
·
Excavation
of trial pit
·
Drainage
work at
·
Site
investigation and pre-drilling works at CR3
·
Diaphragm
wall construction
·
Hoarding
erection
·
Roadworks
at CR3
·
Grout
curtain
·
Sheet-piling
·
Tree
purning
Contract no. HK/2009/01 – Wan Chai Development Phase II – Central – Wan
Chai Bypass at
·
Diaphragm
Wall construction works for both CWB within HKCEC 1
·
Pre-drilling
works for CWB at Stage 2.
·
Pilling
works for CWB at Stage 2.
·
Excavation
and installation of shoring system for CWB top slab.
Contract no. HK/2009/02 – Wan Chai Development Phase II – Central – Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
·
Deep
excavation works below +1mPD for western tunnel portion and below +4mPD for
eastern tunnel portion.
·
Toe
grout, Shear pine, and Pumping test at WCR1 area.
Contract
no. HY/2009/15 – Central-Wanchai Bypass – Tunnel (
·
Diaphragm
wall construction at TS4
·
ELS works
at TS1
·
Pumping
test and ELS preparation works at TPCWAE
·
Night
time protection works at CHT
·
Construction
of dewatering well at
·
Precautionary
works at Abutment A
Contract
no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point Section) and
Island Eastern Corridor Link under FEP-07/364/2009/A
·
Remove
existing dolphin
·
Road
works at
·
Fabrication
of bored piling platform
·
Bored
piling
·
Ground
contamination assessment
·
Pre-drilling
works for bored pile and Diaphragm wall
·
D-wall Construction
·
Sheet
piling for Box Culvert T
·
Construction
works for Box Culvert T
·
Marine
Piling
1.1.1.
Lam Geotechnics
Limited (LGL) has been appointed to work as the Environmental Team (ET) under
Environmental Permit no. EP-364/2009A and Further Environmental permit nos. FEP-01/364/2009, FEP-02/364/2009, FEP-03/364/2009, FEP-04/364/2009/A, FEP-05/364/2009/A, FEP-06/364/2009/A and FEP-07/364/2009/A to implement the Environmental Monitoring and Audit
(EM&A) programme as stipulated in the EM&A Manual of the approved
Environmental Impact Assessment (EIA) Report for Wan Chai Development phase II
and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) and in the EM&A
Manual of the approved EIA Report for Central-Wan Chai Bypass and Island
Eastern Corridor Link (Register No. AEIAR-014/2001).
1.1.2.
This report
presents the environmental monitoring and auditing work carried out in
accordance to the Section 10.3 of EM&A
Manual and “Environmental Monitoring and Audit Requirements” under Particular
Specification Section 27.
1.1.3.
This report documents the finding of EM&A works for Environmental Permit (EP) no. EP-364/2009/A, Further Environmental
Permit (FEP) nos. FEP-01-364/2009, FEP-02/364/2009, FEP-03/364/2009,
FEP-05/364/2009/A, FEP-06/364/2009/A and FEP-07/364/2009/A during the period
28th November to 27th
December 2011. The cut-off date of reporting is at 27th of each reporting
month.
Section
1 Introduction
– details the scope and structure of the report.
Section
2 Project Background
– summarizes background and scope of the project, site description, project
organization and contact details of key personnel during the reporting period.
Section
3 Status of Regulatory
Compliance – summarizes the status of valid
Environmental Permits / Licenses during the reporting period.
Section
4 Monitoring Requirements
– summarizes all monitoring parameters, monitoring methodology and equipment,
monitoring locations, monitoring frequency, criteria and respective event and
action plan and monitoring programmes.
Section
5 Monitoring Results
– summarizes the monitoring results obtained in the reporting period.
Section
6 Compliance Audit
– summarizes the auditing
of monitoring results, all exceedances environmental parameters.
Section
7 Cumulative Construction
Impact due to the Concurrent Projects –
summarizes the relevant
cumulative construction impact due to the concurrent activities of the
concurrent Projects.
Section
8 Site Inspection –
summarizes the findings of weekly site inspections undertaken within the
reporting period, with a review of any
relevant follow-up actions
within the reporting period.
Section
9 Complaints, Notification of
summons and Prosecution – summarizes the cumulative statistics on complaints,
notification of summons and prosecution
Section
10 Conclusion
2.1.1.
“Wan Chai
Development phase II and Central-Wan Chai Bypass” and “Central-Wan Chai Bypass
and Island Eastern Corridor Link” (hereafter called “the Project”) are Designed
Project (DP) under the Environmental Impact Assessment Ordinance (Cap. 499)
(EIAO). The Environmental Impact
Assessment (EIA) Reports for Central-Wan Chai Bypass and
2.1.2.
The key purpose
of Wan Chai Development Phase II (WDII) is to provide land at Wan Chai North
and North Point for construction of the Central-Wan Chai Bypass and Island
Eastern Corridor Link (CWB). Land formed under the project will be developed as
a world-class waterfront promenade joining that at the new Central waterfront
for public enjoyment.
2.1.3.
There is a
compelling and present need for the CWB to provide relief to the very congested
2.2.1.
Design and Construction of Central – Wan Chai Bypass and Island Eastern
Corridor Link under the Project involves the construction and operation of a
trunk road and its road tunnel more than 800m in length between portals that is
shown at Figure 2.1.
2.2.2.
The study area encompasses existing
developments from Central to North Point. The scope of the Central-Wanchai Bypass (CWB)
and Island Eastern Corridor Link (IECL) includes:
·
A dual
three-lane trunk road, approximately 4.5 km in length, and tunnel approximately
3.7 km in length defined from the connection with the existing Rumsey Street
Flyover in Central, through to a connection with the existing Island Eastern
Corridor to the east of the Causeway Bay Typhoon Shelter (CBTS);
·
The
Central Interchange near the Rumsey Street Flyover to provide road connections
to the Central area;
·
Tunnel
control buildings and ventilation buildings;
·
Slip
roads to connect the CWB to the local road system in the Wan Chai North and
·
Associated
road lighting, road signing, traffic control and surveillance system; and
·
Other
associated works.
2.2.3.
The project also
contains various Schedule 2 DPs that, under the EIAO, require Environmental
Permits (Eps) to be granted by the DEP before they may be either constructed or operated. Table 2.1 summarises the
five individual DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.
Table 2.1 Schedule 2 Designated Projects under this
Project
Item |
Designated Project |
EIAO Reference |
Reason for inclusion |
DP1 |
Central-Wanchai
Bypass (CWB) including its road tunnel and slip roads |
Schedule
2, Part I, A.1 and A.7 |
Trunk
road and road tunnel more than 800 m in length |
DP2 |
Road P2
and other roads which are classified as primary/district distributor roads |
Schedule
2, Part I, A.1 |
Primary
/ district distributor roads |
DP3 |
Reclamation
works including associated dredging works |
Schedule
2, Part I, C.1 and C.12 |
Reclamation
more than 5 ha in size and a dredging operation less than 100 m from a
seawater intake point |
DP5 |
Wan Chai
East Sewage Outfall |
Schedule
2, Part I, F.5 and F.6 |
Submarine
sewage pipelines with a total diameter more than 1,200 mm and include a
submarine sewage outfall |
DP6 |
Dredging
for the Cross-harbour Water Mains from Wan Chai to Tsim Sha Tsui |
Schedule
2, Part I, C.12 |
A
dredging operation less than 100 m from a seawater intake point |
2.3.1.
Due to the
multi-contract nature of the Project, there are a number of contracts sub-dividing
the whole works area into different work areas to be commenced. Contractors of individual contracts will be
required by the EP holder to apply Further Environmental Permits such that the impact monitoring stations are sub-divided
accordingly to facilitate the implementation of EM&A programme and to
streamline the EM&A reporting for individual FEP holders correspondingly.
2.3.2.
In the reporting
month, Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section)
was commenced on 13 July 2011. The details of individual contracts are summarized in Table2.2.
Table 2.2 Details of Individual Contracts under the
Project
Contract No. |
Contract Title |
Associated DP(s) |
Construction Commencement Date |
HY/2009/17 |
Central –
Wan Chai Bypass (CWB) at FEHD Whitfield Depot – Advanced piling works. |
DP1 |
5 October 2010 |
HY/2009/18 |
Central –
Wan Chai Bypass (CWB) – Central Interchange |
DP1 |
21 April 2011 |
04/HY/2006 |
Reconstruction
of Bus Terminus near |
DP1 |
September 2010 |
HK/2009/01 |
Wan Chai
Development Phase II – Central – Wan Chai Bypass at |
DP1, DP2 |
25
August 2011 |
HK/2009/02 |
Wan Chai
Development Phase II – Central – Wan Chai Bypass at Wan Chai East(CWB Tunnel)
|
DP1 |
26 April
2011 |
HY/2009/15 |
Central-Wanchai
Bypass – Tunnel ( |
DP1 |
13 July
2011 |
HY/2009/19 |
Central –
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link |
DP1 |
24 March
2011 |
2.4.1.
Civil Engineering and Development Department and Highways Department are
the overall project controllers for the Wan Chai Development Phase II and
Central-Wan Chai Bypass respectively. For the construction phase of the
Project, Project Engineer, Contractor(s), Environmental Team and Independent
Environmental Checker are appointed to manage and control environmental issues.
2.4.2.
The proposed
project organization and lines of communication with respect to environmental
protection works are shown in Figure
2.2. Key personnel and contact particulars are
summarized in Table 2.3:
Table 2.3 Contact Details of Key Personnel
Party |
Role |
Post |
Name |
Contact No. |
Contact Fax |
AECOM |
Engineer
for WDII |
Principal
Resident Engineer |
Mr.
Frankie Fan |
2587
1778 |
2587 1877 |
Engineer
for CWB |
Principal
Resident Engineer |
Mr.
Peter Poon |
3916
1818 |
3529 2829 |
|
Lam Woo &
CO., LTD. |
Contractor
under Contract no. HY/2009/17 |
Project
Manager |
Mr. K.
S. Law |
9090
1378 |
2566 7522 |
Site Agent |
Mr. Tony
Au |
9725
5874 |
2566 7522 |
||
Sub Agent |
Mr.
Johnny Wong |
9725
5870 |
2566 7522 |
||
Chun Wo
– Leader Joint Venture |
Contractor
under Contract no. HK/2009/01 |
Site Agent |
Mr. Paul Yu |
9456 9819 |
2634 1626 |
Operation Manager |
Mr. Lau Yee Ching |
9466 3918 |
|||
Construction Manager |
Mr Jerry Siu |
9493 3664 |
|||
Construction Manager |
Mr Ricky Lai |
9487 6549 |
|||
Construction Manager |
Mr KK Yuen |
3498 1213 |
|||
Environmental Officer (Compliance
Manager) |
Mr. Andy Mak |
9103 2370 |
|||
Environmental Supervisor |
Ms. Kiwi Chan |
6227 8840 |
|||
Chun Wo
– CRGL Joint Venture |
Contractor
under Contract no. HK/2009/02 |
Project
Manager |
Mr. Chan
Sing Cho |
3658-3002 |
2827 9996 |
Site
Agent |
Mr. Mak
Kam Wing |
3658-3044 |
|||
Deputy
Site Agent |
Mr.
Anthony Wu |
3658-3004 |
|||
Quality
& Environmental Manager |
Mr. C.P.
Ho |
3658-3000 |
|||
Environmental
Officer |
Ms Flora
Ng |
3658-3064 |
|||
Chun Wo
– CRGL Joint Venture |
Contractor
under Contract no. HY/2009/19 |
Project
Manager |
Mr.
Rayland Lee |
3758 8879 |
2570 8013 |
Site
Agent |
Mr. Cheung
Kit Cheung |
6909
1555 |
|||
Environmental
Engineer |
Mr. Simon
Wong |
9281
4346 |
|||
Environmental
Manager / Environmental
Officer |
Mr. M.H.
Isa |
9884
0810 |
|||
Leighton
Contractors ( |
Contractor
under Contract no. HY/2009/18 |
Site
Agent |
Mr.
Brian Gillon |
2214 7700 |
|
Deputy
Site Agent |
Mr.
Desmond Sze |
2214 7703 |
|||
Environmental
Officer |
Mr.
Anfernee Chow |
2214 7721 |
|||
Environmental
Supervisor |
Mr.
Dennis Yu |
2214 7738 |
|||
Environmental
Supervisor |
Ryan
Tsui |
2214 7705 |
|||
|
Contractor
under Contract no. HY/2009/15 |
Project
Manager |
Mr. M Y
Wong |
2823
7879 |
2566 2192 |
Site
Agent |
Mr. P J
Fan |
3557
6368 |
|||
Head of
construction |
Mr. Roger
Cheung |
3557
6371 |
|||
Environmental
Officer |
Mr. Daniel
Sin |
3557
6215 |
|||
Environmental
Supervisor |
Mr. Kelven
Yip |
3557
6347 |
|||
Environmental
Supervisor |
Mr. Tim
Fung |
3557
6349 |
|||
|
|
Environmental
Supervisor |
Mr. Hilda
Lau |
3557
6378 |
|
ENVIRON
Hong Kong Limited |
Independent Environmental Checker (IEC) |
Independent Environmental Checker (IEC) |
Mr.
David Yeung |
3743
0788 |
3548 6988 |
Lam Geotechnics Limited |
Environmental Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
2.4.3.
In this reporting month, the principal work activities of individual
contracts are included as follows:
Contract no. HY/2009/17 –
Central – Wan Chai Bypass (CWB) at FEHD Whitfield Depot – Advanced piling works
under FEP-03/364/2009
·
ELS works
for basement construction for pile cap construction.
Contract no. HY/2009/18 – Central
– Wan Chai Bypass (CWB) - Central
Interchange under FEP-05/364/2009/A
·
Instrumentation
works for Manholes and Intake Culvert Survey
·
Excavation
of trial pit
·
Drainage
work
·
Site
investigation and pre-drilling works
·
Diaphragm
wall construction
·
Hoarding
erection
·
Roadworks
·
Grout
curtain
·
Tree
purning
Contract no. HK/2009/01 – Wan Chai
Development Phase II – Central – Wan Chai Bypass at
·
Diaphragm
wall construction works for CWB (stage 1).
·
Pre-drilling
works for CWB (stage 2).
·
Pre-bored
H pilling works for CWB (stage 1).
Contract no. HK/2009/02 – Wan Chai
Development Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
·
Tunnel
bored pile works at WCR1 area
·
Toe grout
at WCR1 area.
·
Shear pin
at WCR1 area.
·
Pumping
test at WCR1 area.
·
King Post
at WCR1 area.
·
West
bulkhead capping beam.
·
Steel
deck support for cooling main.
·
Working
deck B at WCR1.
·
Deep
excavation of CWB at the eastern area of working deck B.
Contract no. HY/2009/15 –
Central-Wanchai Bypass – Tunnel (
·
Seawall
block construction, reclamation work and diaphragm wall construction
preparation works at TS4
·
Diaphragm
wall construction at TS1 and TPCWAE
·
Night
time protection works at CHT
·
Construction
of dewatering well at
·
Precautionary
works at Abutment A
Contract no. HY/2009/19 – Central
– Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor
Link under FEP-07/364/2009/A
·
Preparation
works and concreting of marine piles
·
Fabrication
of bored piling platform
·
Bored
piling
·
Ground
contamination assessment
·
D-wall Construction
·
Sheet
piling for Box Culvert T
·
Construction
works for Box Culvert T
2.4.4.
In coming
reporting month, the principal work activities of individual contracts are
anticipated as follows:
Contract no. HY/2009/17 – Central – Wan Chai Bypass (CWB) at FEHD
Whitfield Depot – Advanced piling works under FEP-03/364/2009
·
ELS works
for basement construction for pile cap construction.
Contract no. HY/2009/18 – Central – Wan Chai
Bypass (CWB) – Central Interchange under FEP-05/364/2009/A
·
Instrumentation
works for Manholes and Intake Culvert Survey
·
Excavation
of trial pit
·
Drainage
work at
·
Site
investigation and pre-drilling works at CR3
·
Diaphragm
wall construction
·
Hoarding
erection
·
Roadworks
at CR3
·
Grout
curtain
·
Sheet-piling
·
Tree
purning
Contract no. HK/2009/01 – Wan Chai Development Phase II – Central – Wan
Chai Bypass at
·
Diaphragm
Wall construction works for both CWB within HKCEC 1
·
Pre-drilling
works for CWB at Stage 2.
·
Pilling
works for CWB at Stage 2.
·
Excavation
and installation of shoring system for CWB top slab.
Contract no. HK/2009/02 – Wan Chai Development Phase II – Central – Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
·
Deep
excavation works below +1mPD for western tunnel portion and below +4mPD for
eastern tunnel portion.
·
Toe
grout, Shear pine, and Pumping test at WCR1 area.
Contract
no. HY/2009/15 – Central-Wanchai Bypass – Tunnel (
·
Diaphragm
wall construction at TS4
·
ELS works
at TS1
·
Pumping
test and ELS preparation works at TPCWAE
·
Night
time protection works at CHT
·
Construction
of dewatering well at
·
Precautionary
works at Abutment A
Contract
no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point Section) and
Island Eastern Corridor Link under
FEP-07/364/2009/A
·
Remove
existing dolphin
·
Road works
at
·
Fabrication
of bored piling platform
·
Bored
piling
·
Ground
contamination assessment
·
Pre-drilling
works for bored pile and Diaphragm wall
·
D-wall Construction
·
Sheet
piling for Box Culvert T
·
Construction
works for Box Culvert T
·
Marine
Piling
3.1.1.
A summary of the
current status on licences and/or permits on environmental protection pertinent
to the Project is shown in Table 3.1.
Permits and/or Licences |
Reference No. |
Issued Date |
Status |
Environmental Permit |
EP-356/2009 |
30 Jul 2009 |
Valid |
Environmental Permit |
EP-364/2009 |
17 Aug 2009 |
Superseded |
Environmental Permit |
EP-364/2009/A |
4 Aug 2010 |
Valid |
Environmental Permit |
EP-376/2009 |
13 Nov
2010 |
Valid |
Further Environmental Permit |
FEP-01/356/2009 |
18 Feb 2010 |
Valid |
Further Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
Valid |
Further Environmental Permit |
FEP-03/356/2009 |
24 Mar 2010 |
Valid |
Further Environmental Permit |
FEP-04/356/2009 |
15 Nov 2010 |
Valid |
Further Environmental Permit |
24 Mar 2010 |
Valid |
|
Further Environmental Permit |
21 Apr 2010 |
Valid |
|
Further Environmental Permit |
12 July 2010 |
Valid |
|
Further Environmental Permit |
14 Oct 2010 |
Surrendered |
|
Further Environmental Permit |
15 Nov 2010 |
Valid |
|
Further Environmental Permit |
22 Nov 2010 |
Valid |
|
Further Environmental Permit |
25 Feb 2011 |
Valid |
3.1.2.
Due to the
multi-contract nature of the Project, the status of permits and/or licences
under the individual contract(s) are presented as below:
Contract no. HY/2009/17 – Central
– Wan Chai Bypass (CWB) at FEHD Whitfield Depot – Advanced piling works under
FEP-03/364/2009
3.1.3.
Summary of the
current status on licences and/or permits on environmental protection pertinent
and submission under FEP-03/364/2009 for contract no. HY/2009/17 showed in Table
3.2 and Table 3.3.
Table
3.2 Cumulative Summary of Valid
Licences and Permits under Contract no. HY/2009/17
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-03/364/2009 |
12 Jul 2010 |
N/A |
Valid |
Notification of Works Under APCO |
319348 |
13 Jul 2010 |
N/A |
Valid |
Discharge Licence |
WT00007212-2010 |
5 Aug 2010 |
5 Aug 2010 – 31 Aug 2015 |
Valid |
Registration as a Waste Producer |
5213-151-L2608-05 |
13 July 2010 |
N/A |
Valid |
Billing Account under Waste Disposal
Ordinance |
7010400 |
16 Mar 2010 |
N/A |
Valid |
Table 3.3 Summary
of submission status under FEP-03/364/2009
EP Condition |
Submission |
Date of
Submission |
Condition 2.6 |
Management Organization
of Main Construction Companies |
18 September 2010 |
Conditions 2.7 and 2.8 |
Submission of works
schedule and location plan |
1 September 2010 |
Condition 2.9 |
Noise Management Plan |
1 September 2010 |
Contract no. 04/HY/2006 – Reconstruction of Bus Terminus
near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A
3.1.4.
The construction works was completed, and the FEP was surrendered by the
Contractor on 11 February 2011.
Contract no.
HK/2009/01 – Wan Chai Development Phase II – Central – Wan Chai Bypass at
3.1.5.
Summary of the
current status on licences and/or permits on environmental protection pertinent
and submission under FEP-02/364/2009 for contract no. HK/2009/01 are shown in Table 3.4 and Table 3.5
Table 3.4 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/01
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
N/A |
Valid |
FEP-02/364/2009 |
21 Apr 2010 |
N/A |
Valid |
|
Notification of Works Under APCO |
313088 |
6 Jan 2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for
non-piling equipment |
GW-RS0680-11 |
22 Jul 2011 |
24 Jul 2011
to 19 Jan 2012 |
Valid |
|
GW-RS0689-11 |
28 Jul 2011 |
29 Jul 2011 to 28 Jan 2012 |
Cancelled |
|
GW-RS0832-11 |
7 Sep 2011 |
03 Sep 2011 to 02 Mar 2012 |
Valid |
|
GW-RS0850-11 |
12 Sept 2011 |
14 Sept 2011 to 13 Mar 2012 |
Valid |
|
GW-RS0851-11 |
12 Sept 2011 |
16 Sept 2011 to 15 Mar 2012 |
Valid |
|
GW-RE0683-11 |
16 Sept
2011 |
20 Sept 2011 to 19 Oct 2012 |
Valid |
|
GW-RE0716-11 |
28 Sept 2011 |
07 Oct 2011 to 29 Mar 2012 |
Valid |
|
GW-RS1031-11 |
02 Nov 2011 |
07 Nov 2011 to 05
May 2012 |
Valid |
|
GW-RS1094-11 |
23 Nov 2011 |
27 Nov 2011 to 26
May 2011 |
Valid |
Discharge Licence |
WT00006220-2010 |
18 Mar 2010 |
31 Mar
2015 |
Valid |
|
WT00009641-2011 |
24 Jul 2011 |
31 Jul 2016 |
Valid |
Billing account
under Waste Disposal Ordinance |
7010069 |
21 Jan 2010 |
N/A |
Valid |
Registration as a Chemical Waste Producer |
WPN5213-134-C3585-01 |
21 Jan
2010 |
N/A |
Valid |
Table 3.5 Summary
of submission status under FEP-02/364/2009
EP Condition |
Submission |
Date of
Submission |
Special Conditions, Clause 2.7 & 2.8 |
Works Schedule and Location Plan |
18 May
2011 |
Special Conditions, Clause 2.6 |
Environmental Management Organization Chart |
18 May 2011 |
Special Conditions, Clause 2.6 |
Commencement Date of Works |
25 Jun 2011 |
Special Conditions, Clause 2.9 |
Noise Management Plan |
10 Jun 2011 |
Contract no.
HK/2009/02 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan
Chai East (CWB Tunnel) under FEP-01/364/2009
3.1.6.
Summary of the
current status on licences and/or permits on environmental protection pertinent
and submission under FEP-01/364/2009 for contract no. HK/2009/02 are shown in Table 3.6 and Table 3.7.
Table 3.6 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/02
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further
Environmental Permit |
FEP-03/356/2009 |
24 Mar 2010 |
N/A |
Valid |
FEP-01/364/2009 |
24 Mar 2010 |
N/A |
Valid |
|
Notification
of Works Under APCO |
313962 |
2 Feb
2010 |
N/A |
Valid |
Construction
Noise Permit (CNP) for piling equipment |
PP-RS0011-11 |
27 April
2011 |
1 June
2011 to 30 Nov
2011 |
Valid |
Construction
Noise Permit (CNP) for non-piling equipment |
GW-RS0579-11 |
22 June
2011 |
17 July
2011 to 16 Jan 2012 |
Valid |
|
GW-RS0649-11 |
22 July
2011 |
1 Aug
2011 to 31 Jan 2012 |
Valid |
|
GW-RS0716-11 |
2 Aug
2011 |
12 Aug
2011 to 11 Feb 2012 |
Valid |
|
GW-RS0723-11 |
12 Aug
2011 |
15 Aug
2011 to 14 Feb 2012 |
Valid |
|
GW-RS0833-11 |
8 Sept
2011 |
10 Sept
2011 to 4 Mar 2012 |
Valid |
|
GW-RE0710-11 |
30 Sept
2011 |
1 Nov
2011 to 30 Apr 2012 |
Valid |
|
GW-RS0918-11 |
7 Oct
2011 |
10 Oct
2011 to 9 Apr 2012 |
Valid |
|
GW-RS0930-11 |
11 Oct
2011 |
1 Nov
2011 to 30 Apr 2012 |
Valid |
|
GW-RS0931-11 |
7 Oct
2011 |
10 Oct
2011 to 9 Apr 2012 |
Valid |
|
GW-RS0941-11 |
20 Oct
2011 |
23 Nov
2011 to 22 May 2012 |
Valid |
|
GW-RS0955-11 |
14 Oct
2011 |
23 Nov
2011 to 22 May 2012 |
Valid |
|
GW-RS0968-11 |
20 Oct
2011 |
18 Nov
2011 to 17 May 2012 |
Valid |
|
GW-RS0983-11 |
24 Oct
2011 |
26 Oct
2011 to 23 April 2012 |
Valid |
|
GW-RS0984-11 |
25 Oct 2011 |
30 Oct
2011 to 27 April 2012 |
Valid |
|
GW-RS1028-11 |
3 Nov
2011 |
7 Dec
2011 to 6 June 2012 |
Valid |
|
GW-RS1052-11 |
18 Nov
2011 |
21 Nov
2011 to 18 May 2012 |
Valid |
|
GW-RS1116-11 |
28 Nov
2011 |
13 Dec
2011 to 12 June 2012 |
Valid |
|
GW-RS1111-11 |
28 Nov
2011 |
29 Nov
2011 to 28 May 2012 |
Valid |
|
GW-RS1116-11 |
28 Nov
2011 |
13 Dec
2011 to 12 June 2012 |
Valid |
Discharge
Licence |
WT00006249-2010 |
22 Mar
2010 |
31 Mar
2015 |
Valid |
|
WT00006436-2010 |
15 Apr
2010 |
30 Apr
2015 |
Valid |
|
WT00006673-2010 |
14 May
2010 |
31 Mar
2015 |
Valid |
|
WT00006757-2010 |
28 May
2010 |
31 May
2015 |
Valid |
|
WT00007129-2010 |
28 July
2010 |
31 Jul
2015 |
Valid |
|
WT00008982-2011 |
26 April
2011 |
30 April
2016 |
Valid |
|
WT00009691-2011 |
1 Aug
2011 |
31 July
2016 |
Valid |
Billing
Account under Waste Disposal Ordinance (Land) |
7010255 |
10 Feb
2010 |
N/A |
Valid |
Registration
as Chemical Waste Producer (Wan Chai) |
WPN5213-135-C3593-01 |
10 Mar 2010 |
N/A |
Valid |
Registration
as Chemical Waste Producer (TKO 137) |
WPN5213-839-C3593-02 |
22 Sep
2010 |
N/A |
Valid |
Table 3.7 Summary
of submission status under FEP-01/364/2009
EP Condition |
Submission |
Date of
Submission |
Special Conditions, Clause 2.7 & 2.8 |
Works Schedule and Location Plan |
14 Jun 2011 |
Special Conditions, Clause 2.6 |
Environmental Management Organization Chart |
14 Jun 2011 |
Special Conditions, Clause 2.6 |
Commencement Date of Works |
21 Jun 2011 |
Special Conditions, Clause 2.9 |
Noise Management Plan |
28 Jun 2011 |
Condition 2.11 |
Landscape Plan |
23 Aug 2011 |
Condition 2.9 |
Noise Management Plan (Rev.A) |
28-Sep-11 |
Contract no. HY/2009/18 – Central – Wan Chai Bypass (CWB) – Central
Interchange under FEP-05/364/2009/A
3.1.7.
Summary of the
current status on licences and/or permits on environmental protection pertinent
and submission under FEP-05/364/2009A for contract no.
HY/2009/18 are shown in
Table 3.8 and Table 3.9.
Table 3.8 Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/18
Permit / Licence / Notification / Approval |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-05/364/2009/A |
15 Nov 2010 |
Permit issued |
Valid |
Notification of Works Under APCO |
322293 |
07 Oct 2010 |
Notified |
Valid |
Construction Noise Permit (CNP) for non-piling equipment |
GW-RS0993-11 |
28 Oct 2011 |
28 Oct 2011 – |
Valid |
Discharge Licence |
WT00008229-2011 |
13 Jan 2011 |
31 Jan 2016 |
Valid |
Registration as a Waste Producer |
WPN: 8335-121-L1048-04 |
17 Dec 2010 |
N/A |
Registration completed |
Billing Account under Waste Disposal
Ordinance (Land) |
Account No.: 7011587 |
11 Oct 2010 |
Account approved |
Valid |
Table 3.9 Summary
of submission status under FEP-05/364/2009/A
EP Condition |
Submission |
Date of
Submission |
Condition 2.9 |
Noise Management Plan |
01 March 2011 |
Condition 2.10 |
Landscape Plan (Rev. 4) |
3 August 2011 |
Contract
no. HY/2009/15 – Central-Wanchai Bypass – Tunnel (
3.1.8.
Summary of the
current status on licences and/or permits on environmental protection pertinent
and submission under FEP-06/364/2009/A for contract no. HY/2009/15 are shown in Table 3.10 and Table 3.11
Table 3.10 Cumulative Summary of Valid Licences and
Permits under Contract no. HY/2009/15
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-04/356/2009 |
22 Nov
2010 |
N/A |
Valid |
FEP-06/364/2009/A |
22 Nov
2010 |
N/A |
Valid |
|
Notification of Works Under APCO |
321822 |
24 Sep 2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for
non-piling equipment |
GW-RS0749-11 |
11 Aug 2011 |
15 Aug 2011 to 7 Feb 2012 |
Valid |
|
GW-RS1021-11 |
4 Nov 2011 |
10 Nov 2011 to 9 May 2012 |
Valid |
|
GW-RS0847-11 |
14 Sep 2011 |
19 Sep 2011 to 16 Mar 2012 |
Cancelled |
|
GW-RS1153-11 |
9 Dec 2011 |
12 Dec 2011 to 16 Mar 2012 |
Valid |
|
GW-RS0858-11 |
16 Sep 2011 |
18 Sep 2011 to 16 Mar 2012 |
Valid |
|
GW-RS1211-11 |
22 Dec 2011 |
24 Dec 2011 to 21 Jun 2012 |
Valid |
|
GW-RS0883-11 |
4 Oct 2011 |
5 Oct 2011to 4 Apr 2012 |
Valid |
|
GW-RS0820-11 |
5 Sep 2011 |
8
Sep 2011 to 7 Mar 2012 |
Valid |
|
GW-RS1149-11 |
7 Dec 2011 |
8 Dec 2011 to 7 Jun 2012 |
Valid |
|
GW-RS1138-11 |
7 Dec 2011 |
8 Dec 2011 to 21 May 2012 |
Valid |
|
GW-RS1190-11 |
30 Dec 2011 |
22 Dec 2011 to 21 Jun 2012 |
Valid |
Construction Noise Permit (CNP) for Loading Works at Siu Ho Wan |
GW-RS0997-11 |
2 Nov 2011 |
2 Nov 2011 to 2 May 2012 |
Valid |
Construction Noise Permit (CNP) for Dredging and Filling |
GW-RS1021-11 |
4 Nov 2011 |
10 Nov 2011 to 9 May 2012 |
Valid |
Registration as a Chemical Waste Producer |
WPN: 5213-147-C1169-35 |
15 Nov 2010 |
N/A |
Valid |
Billing Account under Waste
Disposal Ordinance |
7011553 |
30 Sep 2010 |
27 Sep 2010 to 27 Jan 2016 |
Valid |
Billing Account under Waste
Disposal Ordinance (Dumping by Vessel) |
7011761 |
28 Apr 2011 |
1 May 2011 to 30 Oct 2011 |
Valid |
Water Discharge Licence (Discharge
at Portion VII) |
WT00008780-2011 |
22 Mar 2011 |
22 Mar 2011 to 31 Mar 2016 |
Valid |
Water Discharge Licence (Discharge
at |
WT00010482-2011 |
30 Sep 2011 |
30 Sep 2011 to 30 Sep 2013 |
Valid |
Water Discharge Licence (Discharge
at TPCWAE) |
WT00011322-2011 |
15 Dec 2011 |
15 Dec 2011 to 31 Dec 2013 |
Valid |
Table 3.11 Summary
of submission status under FEP-06/364/2009/A
EP Condition |
Submission |
Date of
Submission |
Condition
2.6 |
Management
Organization of Main Construction Companies |
11 Mar 2011 |
Amendment
for Management Organization of Main Construction Companies |
16 May 2011 |
|
Condition
2.7 |
Works Schedule |
15 Mar 2011 |
Condition
2.8 |
Location
Plan |
15 Mar 2011 |
Condition
2.23 |
Noise
Management Plan |
6 May 2011 |
Contract no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
3.1.9.
The current status
on licences and/or permits on environmental protection pertinent and submission under
FEP-07/364/2009/A for contract no. HY/2009/19 are shown in Table 3.12 and Table 3.13.
Table 3.12 Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/19
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
25 Feb 2011 |
N/A |
Valid |
|
Notification of Works Under APCO |
326160 |
24
Jan 2011 |
N/A |
Valid |
Registration as a Waste Producer |
7012306 |
10 Feb 2011 |
N/A |
Valid |
Registration as Chemical Waste
Producer |
5213-151-C3654-01 |
24 Mar 2011 |
N/A |
Valid |
Application for Vessel Disposal |
7012306 |
21 July 2011 |
N/A |
Valid |
Construction Noise Permit (CNP) |
GW-RS1097-11 |
22-Nov-11 |
07-May-12 |
Valid |
Water Discharge Licence |
WT00010093-2011 |
31-Aug-11 |
30-Sep-16 |
Valid |
|
WT00010865-2011 |
3-Nov-11 |
30-Nov-16 |
Valid |
Table 3.13 Summary
of submission status under FEP-07/364/2009/A
EP Condition |
Submission |
Date of
Submission |
Condition 2.9 |
Noise Management Plan |
02 Jun 2011 |
Condition 2.13 |
Landscape Plan |
7 July
2011 |
Condition 2.9 |
Noise Management Plan(Rev.2) |
28-Oct-11 |
Noise Monitoring Stations
4.1.1.
The noise
monitoring stations for the Project are listed and shown in Table
4.1 and Figure 4.1. Appendix 4.1 shows the established Action/Limit Levels for the monitoring works.
Table
4.1 Noise Monitoring Stations
Station |
Description |
M1a |
Harbour Road Sports Centre |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire Station |
M4b |
Victoria Centre |
M5b |
|
M6 |
HK |
M7e |
International Finance Centre
(Eastern End of Podium) |
M7w |
International Finance Centre
(Western End of Podium) |
Real time Noise Monitoring Stations
4.1.2.
Review of feasibility on the real time noise monitoring stations was
conducted in July with IEC. Station, RTN1a, Tung Lo Wan fireboat Station was
found not appropriate to be a monitoring station for monitoring the IECL Piling
works and Demolition after visited.
4.1.3.
The noise
monitoring stations for the Project are listed and shown in Table 4.2 and Figure 4.1.. Appendix 4.1 shows the established Action/Limit Levels for the
monitoring works.
Table 4.2 Real
Time Noise
Monitoring Stations
District |
Station |
Description |
Tin Hau |
RTN1 |
FEHD Hong Kong Transport Section Whitefield Depot |
North Point |
RTN2 |
Oil Street Community Liaison Centre |
Noise Monitoring Parameters, Frequency and Duration
4.1.4.
The
construction noise level shall be measured in terms of the A-weighted
equivalent continuous sound
pressure level (Leq). Leq (30 minutes) shall be used as
the monitoring parameter for the time period between 0700 and 1900 hours on normal weekdays. For
all other time periods, Leq (5 minutes) shall be employed for
comparison with the Noise Control Ordinance (NCO) criteria. Supplementary information for data auditing,
statistical results such as L10 and L90 shall also be
obtained for reference.
4.1.5.
Noise monitoring
shall be carried out at all the designated monitoring stations. The monitoring
frequency shall depend on the scale of the construction activities. The
following is an initial guide on the regular monitoring frequency for each
station on a weekly basis when noise generating activities are underway:
·
One set of measurements between
0700 and 1900 hours on normal weekdays.
4.1.6.
Real time noise
shall be carried out at the designated monitoring stations. The following is an
initial guide on the regular monitoring frequency for each station on a 24
hours daily basis when noise generating activities are underway:
·
One set of measurements between
0700 and 1900 hours on normal weekdays.
·
One set of measurements between
1900 and 2300 hours on normal weekdays and 0700 and 2300 hours on public
holidays.
·
One set of measurements between
2300 and 0700 hours on next day on everyday.
4.1.7.
If construction
works are extended to include works during the hours of 1900 – 0700 as well as
public holidays and Sundays, additional weekly impact monitoring shall be
carried out during respective restricted hours periods. Applicable permits
under NCO shall be obtained by the Contractor.
Monitoring Equipment
4.1.8.
As referred to
in the Technical Memorandum ™ issued under the NCO, sound level meters in
compliance with the International Electrotechnical Commission Publications 651:
1979 (Type 1) and 804: 1985 (Type 1) specifications shall be used for carrying
out the noise monitoring. Immediately prior to and following each noise
measurement the accuracy of the sound level meter shall be checked using an
acoustic calibrator generating a known sound pressure level at a known
frequency. Measurements may be accepted as valid only if the calibration level
from before and after the noise measurement agree to within 1.0 dB.
4.1.9.
Noise
measurements shall not be made in fog, rain, wind with a steady speed exceeding
5 m/s or wind with gusts exceeding 10 m/s. The wind speed shall be checked with
a portable wind speed meter capable of measuring the wind speed in m/s.
4.1.10. The sound level meter shall be checked using an
acoustic calibrator generating a known sound pressure level at a known
frequency before deployment to the site and during each site visit.
Measurements July be accepted as valid only if the calibration level from
before and after the noise measurement agree to within 1.0 dB.
Air Quality Monitoring Stations
4.2.1.
The air
monitoring stations for the Project are listed and shown in Table
4.3 and Figure 4.1.. Appendix 4.1 shows the
established Action/Limit Levels for the monitoring works.
Table 4.3 Air
Monitoring Stations
Station ID |
Monitoring Location |
Description |
CMA1b |
Oil Street Community Liaison Centre |
North Point (Re-commenced on 14
November 2011) |
CMA2a |
|
|
CMA3a |
CWB PRE Site Office * |
|
CMA4a |
Society for the Prevention of Cruelty to Animals |
Wan Chai |
CMA5a |
|
Wan Chai |
MA1e |
International Finance Centre
(Eastern End of Podium) |
Central |
MA1w |
International Finance Centre
(western End of Podium) |
Central |
Remarks:
As per the ENPC meeting in March 2011, the monitoring stations CMA3a – Future
CWB site office at Wanchai Waterfront Promenade was renamed as remark.
Air Monitoring Parameters, Frequency and Duration
4.2.2.
One-hour and
24-hour TSP levels should be measured to indicate the impacts of construction
dust on air quality. The 24-hour TSP levels shall be measured by following the
standard high volume sampling method as set out in the Title 40 of the Code of
Federal Regulations, Chapter 1 (Part 50), Appendix B.
4.2.3.
All relevant
data including temperature, pressure, weather conditions, elapsed-time meter
reading for the start and stop of the sampler, identification and weight of the
filter paper, and any other local atmospheric factors affecting or affected by
site conditions, etc., shall be recorded down in detail.
4.2.4.
For regular
impact monitoring, the sampling frequency of at least once in every six-days,
shall be strictly observed at all the monitoring stations for 24-hour TSP
monitoring. For 1-hour TSP monitoring, the sampling frequency of at least three
times in every six-days should be undertaken when the highest dust impact
occurs.
Sampling Procedure and Monitoring Equipment
4.2.5.
High volume
samplers (HVSs) in compliance with the following specifications shall be used
for carrying out the 1-hour and 24-hour TSP monitoring:
·
0.6 – 1.7 m3 per minute
adjustable flow range;
·
Equipped with a timing / control
device with +/- 5 minutes accuracy for 24 hours operation;
·
Installed with elapsed-time meter
with +/- 2 minutes accuracy for 24 hours operation;
·
Capable of providing a minimum
exposed area of 406 cm2;
·
Flow control accuracy: +/- 2.5%
deviation over 24-hour sampling period;
·
Equipped with a shelter to
protect the filter and sampler;
·
Incorporated with an electronic
mass flow rate controller or other equivalent devices;
·
Equipped with a flow recorder for
continuous monitoring;
·
Provided with a peaked roof
inlet;
·
Incorporated with a manometer;
·
Able to hold and seal the filter
paper to the sampler housing at horizontal position;
·
Easily changeable filter; and
·
Capable of operating continuously
for a 24-hour period.
4.2.6.
Initial
calibration of dust monitoring equipment shall be conducted upon installation
and thereafter at bi-monthly intervals. The transfer standard shall be traceable
to the internationally recognized primary standard and be calibrated annually.
The concern parties such as IEC shall properly document the calibration data
for future reference. All the data should be converted into standard
temperature and pressure condition.
Laboratory Measurement / Analysis
4.2.7.
A clean
laboratory with constant temperature and humidity control, and equipped with
necessary measuring and conditioning instruments to handle the dust samples
collected, shall be available for sample analysis, and equipment calibration
and maintenance. The laboratory should be HOKLAS accredited.
4.2.8.
Filter paper of
size 8” x 10” shall be labelled before sampling. It shall be a clean filter
paper with no pinholes, and shall be conditioned in a humidity-controlled chamber
for over 24-hours and be pre-weighed before use for the sampling.
4.2.9.
After sampling,
the filter paper loaded with dust shall be kept in a clean and tightly sealed
plastic bag. The filter paper shall then be returned to the laboratory for
reconditioning in the humidity controlled chamber followed by accurate weighing
by an electronic balance with readout down to 0.1 mg. The balance shall be
regularly calibrated against a traceable standard.
4.2.10. All the collected samples shall be kept in a good
condition for 6 months before disposal.
4.2.11. Current calibration certificates of equipments are
presented in Appendix
4.2.
5.0.1.
The
environmental monitoring will be implemented based on the division of works
areas of each designed project managed under different contracts with separate
FEP applied by individual contractors.
Overall layout showing work areas of various contracts, latest status of
work commencement and monitoring stations is shown in Figure
2.1 and Figure 4.1. The monitoring results
are presented in according to the Individual Contract(s).
5.0.2.
In the reporting
month, the concurrent contracts are as follows:
Contract no. HY/2009/15 – Central-Wanchai Bypass – Tunnel (
Contract no.
HY/2009/17 – Central – Wan Chai Bypass (CWB) at FEHD Whitfield Depot – Advanced
piling works under FEP-03/364/2009
Contract no.
HY/2009/18 – Central – Wan Chai Bypass (CWB) – Central Interchange under
FEP-05/364/2009/A
Contract no.
HY/2009/19 – Central – Wanchai Bypass Tunnel (North
Point Section) and Island Eastern Corridor Link under FEP-07/364/2009
Contract no.
HK/2009/01 – Wan Chai Development Phase II – Central – Wan Chai Bypass at
Contract no.
HK/2009/02 Wan Chai Development Phase II – Central-Wan Chai Bypass at Wan Chai
East
5.0.3.
The environment
monitoring schedules for reporting month and coming month are presented in Appendix
5.1.
5.1.1.
The noise
monitoring at stations were M1a and M5b during day time, M3a, M4b, M5b
and M6 during restricted hour were rescheduled on 13 October 2011 due to rain.
Contract no. HY/2009/17 –Central – Wan Chai Bypass (CWB) at FEHD
Whitfield Depot – Advanced piling works under FEP-03/364/2009
5.1.2.
The proposed
division of noise monitoring stations for Contract no. HY/2009/17 are
summarized in Table 5.1 below:
Table 5.1 Noise Monitoring Stations for Contract no. HY/2009/17
Station |
Description |
M4b |
Victoria
Centre |
5.1.3.
One
action level exceedance was recorded regarding one noise complaint
regarding to noise were received on 20 December 2011.
5.1.4.
No limit level
exceedance was recorded during day time and restricted hour period in the
reporting month. Noise monitoring results measured in this reporting period are
reviewed and summarized. Details of
noise monitoring results and graphical presentation can be referred in Appendix 5.2.
Contract no. HY/2009/18 – Central – Wan Chai
Bypass (CWB) – Central Interchange under FEP-05/364/2009/A
5.1.5.
Noise monitoring
for the Central Interchange works under contract no. HY/2009/18 was commenced
on 22 April 2011.The proposed division of noise monitoring stations for
Contract no. HY/2009/18 are summarized in Table 5.2 below:
Table 5.2
Noise Monitoring Stations for Contract no. HY/2009/18
Station |
Description |
M7e |
International
Finance Centre (Eastern End of Podium) |
M7w |
International
Finance Centre (Western End of Podium) |
5.1.6.
One non-project related limit level exceedance was recorded on 20 December
2011 at M7e during day time. Since traffic noise contributed in front of car
park of IFC. It was considered the exceedance was not project related.
5.1.7. Noise monitoring results measured
in this reporting period are reviewed and summarized. Details of noise monitoring results and
graphical presentation can be referred in Appendix 5.2.
Details of the Notification of Exceedance can be referred in Appendix
6.2.
Contract no. HK/2009/01 – Wan Chai Development Phase II – Central – Wan
Chai Bypass at Hong Kong Convention and Exhibition Centre – Tunnel Works under
FEP-02/364/2009 and Contract no. HK/2009/02 – Wan Chai Development Phase II –
Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
5.1.8.
The commencement
of construction works for Contract no. HK/2009/01 under FEP-02/364/2009 is on 25 August 2011 and HK/2009/02 under FEP-01/364/2009 is on 26
April 2011. The proposed division of noise monitoring stations are summarized
in Table
5.3 below.
Table 5.3
Noise Monitoring Station for Contract no HK/2009/01 and HK/2009/02
Station |
Description |
M1a |
Harbour
Road Sports Centre |
5.1.9.
Two limit level exceedances were recorded at M1a on
29 November and 6 December 2011 during restricted hour for the contractor of
HK/2009/02. Major noise source was contributed from
5.1.10.
Noise monitoring results measured in this reporting
period are reviewed and summarized.
Details of noise monitoring results and graphical presentation can be
referred in Appendix 5.2. Details of the Notification of Exceedance can be referred in Appendix
6.2.
Contract no. HY/2009/15 – Central-Wanchai
Bypass – Tunnel (
5.1.11.
The commencement of construction works for Contract
no. HY/2009/15 under FEP-06/364/2009/A was on 13
July 2011. Noise monitoring was commenced on 13 July 2011.
The proposed divisions of noise monitoring stations
are summarized in Table 5.4 below.
Table
5.4 Noise
Monitoring Stations for Contract
no. HY/2009/15
Station |
Description |
M2b |
Noon Gun
Area |
M3a |
Tung Lo
Wan Fire Station |
5.1.12.
No action level and limit level exceedance was recorded
in the reporting month. Noise monitoring results measured in this reporting
period are reviewed and summarized.
Details of noise monitoring results and graphical presentation can be
referred in Appendix
5.2
Contract no. HY/2009/19 – Central
– Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/A
5.1.13. Noise
monitoring for the tunnel works under contract no. HY/2009/19 was commenced on
24 April 2011. The proposed division of noise monitoring stations are
summarized in Table 5.5 below.
Table 5.5
Noise Monitoring Stations
for Contract
no. HY/2009/19
Station |
Description |
M3a |
Tung Lo
Wan Fire Station |
M4b |
Victoria
Centre |
M5b |
|
M6 |
HK |
5.1.14.
One
action level exceedance was recorded regarding one noise complaint
regarding to noise were received on 20 December 2011.
5.1.15.
No limit level exceedance was recorded in the reporting month. Noise monitoring results measured in this reporting
period are reviewed and summarized.
Details of noise monitoring results and graphical presentation can be
referred in Appendix
5.2
5.2.1.
No construction
activity was conducted during night time period (2300 to 0700) in this
reporting month.
Contract no. HY/2009/17 –Central – Wan Chai Bypass (CWB) at FEHD
Whitfield Depot – Advanced piling works under FEP-03/364/2009 and
Contract no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point Section)
and Island Eastern Corridor Link under
FEP-07/364/2009/A
Table 5.6 Real Time Noise
Monitoring Stations
for Contract
no. HY/2009/17
Location
ID |
District |
Description |
RTN1 |
Tin
Hau |
FEHD Hong Kong Transport Section
Whitefield Depot |
Real time noise monitoring results and graphical
presentation during night time period are for information only.
5.2.3.
No action and limit level exceedance were recorded in the reporting
period. Real time noise monitoring results measured in this reporting period
are reviewed and summarized. Details of real time noise monitoring results and
graphical presentation can be referred to Appendix 5.4 .
5.2.4.
The proposed
division of noise monitoring stations are summarized in Table 5.7
below. Real time noise monitoring for major construction works under contract
no. HY/2009/19 was commenced on 24 April 2011.
Table 5.7 Real Time Noise
Monitoring Stations
for Contract
no. HY/2009/19
Location
ID |
District |
Description |
RTN1 |
Tin
Hau |
FEHD Hong Kong Transport Section
Whitefield Depot |
RTN2 |
North Point |
|
Real time noise
monitoring results and graphical presentation during night time period are for
information only.
5.2.5.
No action and limit level exceedance were recorded in the reporting
period. Real time noise monitoring results measured in
this reporting period are reviewed and summarized. Details of real time noise
monitoring results and graphical presentation can be referred to Appendix 5.4 .
Contract no. HY/2009/17 –Central – Wan Chai Bypass (CWB) at FEHD
Whitfield Depot – Advanced piling works under
FEP-03/364/2009
5.3.1
The proposed
division of air monitoring stations are summarized in Table 5.8 below. Air
monitoring for the piling works under contract no. HY/2009/17 was commenced on
8 October 2010.
Table 5.8
Air
Monitoring Station for Contract no. HY/2009/17
Station |
Description |
CMA1b |
Oil Street Community Liaison Centre |
CMA2a |
|
5.3.2
Due to lack of electricity supply, 24hr-TSP at CMA2a was rescheduled
from 12 December 2011 to 13 December 2011
5.3.3
No exceedance
was recorded in the reporting month. Air quality monitoring results measured in
this reporting period are reviewed and summarized. Details of air monitoring results and
graphical presentation can be referred in Appendix 5.3.
Contract no. HY/2009/18 – Central – Wan Chai
Bypass (CWB) – Central Interchange under FEP-05/364/2009/A
5.3.4
Air monitoring
for the Central Interchange works under contract no. HY/2009/18 was commenced
on 21 April 2011.The proposed division of air monitoring stations are
summarized in Table 5.9 below.
Table 5.9
Air
Monitoring Stations for Contract no. HY/2009/18
Station |
Description |
MA1e |
International
Finance Centre (Eastern End of Podium) |
MA1w |
International
Finance Centre (Western End of Podium) |
5.3.5
No exceedance
was recorded in the reporting month. Air quality monitoring results measured in
this reporting period are reviewed and summarized. Details of air monitoring results and
graphical presentation can be referred in Appendix 5.3.
Contract no. HK/2009/01 – Wan Chai Development Phase II – Central – Wan
Chai Bypass at
5.3.6
The commencement
of construction works for Contract no. HK/2009/01 under FEP-02/364/2009 is on 25 August 2011. Air quality monitoring was commenced on 25 August
2011. The proposed division of air monitoring stations are summarized in Table
5.10 below.
Table 5.10
Air
Monitoring Station for Contract no. HK/2009/01
Station |
Description |
CMA5a |
Children
Playgrounds opposite to |
5.3.7
No exceedance
was recorded in the reporting month. Air quality monitoring results measured in
this reporting period are reviewed and summarized. Details of air monitoring results and
graphical presentation can be referred in Appendix 5.3.
Contract no. HK/2009/02 – Wan Chai Development Phase II – Central – Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
5.3.8
The commencement
of construction works for HK/2009/02 under FEP-01/364/2009 is on 26 April 2011.
The proposed division of air monitoring stations are summarized in Table
5.11 below.
Table 5.11
Air
Monitoring Station for Contract no. HK/2009/02
Station |
Description |
CMA4a |
Society
for the Prevention of Cruelty to Animals |
5.3.9
No exceedance
was recorded in the reporting month. Air quality monitoring results measured in
this reporting period are reviewed and summarized. Details of air monitoring results and
graphical presentation can be referred in Appendix 5.3.
Contract no. HY/2009/15 – Central-Wanchai
Bypass – Tunnel (
5.3.10 The commencement of construction works for Contract
no. HY/2009/15 under FEP-06/364/2009/A was on 13 July 2011. Air quality
monitoring was commenced on 14 July 2011. The proposed division of air monitoring stations are
summarized in Table 5.12 below.
Table
5.12 Air Monitoring Station for Contract
no. HY/2009/15
Station |
Description |
CMA3a |
CWB PRE
Site Office |
No exceedance was recorded in the reporting month. Air quality
monitoring results measured in this reporting period are reviewed and
summarized. Details of air monitoring
results and graphical presentation can be referred in Appendix 5.3.
Contract no. HY/2009/19 – Central
– Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor
Link under FEP-07/364/2009/A
5.3.11
The proposed
division of air monitoring stations are summarized in Table 5.13 below. Air
monitoring for the tunnel works under contract no. HY/2009/19 was commenced on
26 April 2011.
Table 5.13
Air Monitoring
Stations
for Contract
no. HY/2009/19
Station |
Description |
CMA1b |
Oil St
Community Liaison Centre |
CMA2a |
|
5.3.12
24-hr TSP monitoring at CMA2a was re-scheduled from 12 Dec to 13 Dec 11.
5.3.13
No exceedance
was recorded at CMA2a in the reporting month. Air quality monitoring results
measured in this reporting period are reviewed and summarized. Details of air monitoring results and
graphical presentation can be referred in Appendix 5.3.
Contract no. HY/2009/17 –Central – Wan Chai
Bypass (CWB) at FEHD Whitfield Depot – Advanced piling works under FEP-03/364/2009
5.4.1.
No Inert and
non-inert C&D waste was disposed in the reporting month. Details of the
waste flow table are summarized in Table 5.14
Table 5.14 Details
of Waste Disposal for Contract no. HY/2009/17
Waste Type |
Quantity
this month, m3 |
Cumulative
Quantity-to-Date, m3 |
Disposal
/ Dumping Grounds |
Inert
C&D materials disposed |
NIL |
NIL |
N/A |
Inert
C&D materials recycled |
N/A |
||
Non-inert
C&D materials disposed |
NIL |
NIL |
N/A |
Non-inert
C&D materials recycled |
NIL |
NIL |
N/A |
Chemical
waste disposed |
N/A |
N/A |
N/A |
Contract nos. HK/2009/01
– Wan Chai Development Phase II – Central – Wan Chai Bypass at
5.4.2.
Inert and
non-inert C&D waste was disposed of in this reporting month. Details of the
waste flow table are summarized in Table 5.15.
Table 5.15 Details
of Waste Disposal for Contract no. HK/2009/01
Inert
C&D materials disposed |
536.10 |
5764.18 |
TKO137, TM38 |
Inert
C&D materials recycled |
NIL |
NIL |
N/A |
Non-inert
C&D materials disposed |
29.72 |
168.98 |
SENT Landfill |
Non-inert
C&D materials recycled |
8560 |
19023 |
N/A |
Chemical
waste disposed |
220 |
1520 |
Kwun Kee (Chemical Waste Collector) |
Contract no.
HK/2009/02 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan
Chai East (CWB Tunnel) under FEP-01/364/2009
5.4.3.
Inert C&D &
non-inert C&D waste was disposed of in this reporting month. Details of the
waste flow table are summarized in Table 5.16.
Table
5.16 Details of Waste Disposal for Contract no.
HK/2009/02
Inert
C&D materials disposed |
5,239 |
62,689 |
TKO137, TM 38 |
Inert
C&D materials recycled |
NIL |
NIL |
N/A |
Non-inert
C&D materials disposed |
35 |
126 |
SENT Landfill |
Non-inert
C&D materials recycled |
NIL |
NIL |
N/A |
Chemical
waste disposed |
NIL |
1,104 |
N/A |
Contract no. HY/2009/18 – Central – Wan Chai Bypass (CWB) – Central
Interchange under FEP-05/364/2009/A
5.4.4.
Inert C&D
and non-inert C&D waste was disposed of in this reporting month. Details of
the waste flow table are summarized in Table 5.17.
Table 5.17 Details
of Waste Disposal for Contract no. HY/2009/18
Inert
C&D materials disposed |
1381 |
10751.1 |
T.K.O. 137 |
Inert
C&D materials recycled |
N/A |
||
Non-inert
C&D materials disposed |
5 |
202.6 |
SENT Landfill |
Non-inert
C&D materials recycled |
N/A |
||
Chemical
waste disposed |
N/A |
Contract no. HY/2009/15 – Central-Wanchai Bypass – Tunnel (
5.4.5.
Inert & Non-inert C&D wastes were
disposed of in this reporting month. Details
of the waste flow table are summarized in Table 5.18.
Table 5.18 Details
of Waste Disposal for Contract no. HY/2009/15
Inert
C&D materials disposed |
310.4 |
2770 |
TKO137 FB |
|
3881.7 |
19,162.8 |
Tuen Mun Area 38 |
Inert
C&D materials recycled |
NIL |
413 |
N/A |
Non-inert
C&D materials disposed |
10.8 |
88 |
SENT Landfill |
Non-inert
C&D materials recycled |
150 |
211.3 |
N/A |
Chemical
waste disposed |
2,200 |
6,000 |
N/A |
Contract
no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point Section) and
Island Eastern Corridor Link under FEP-07/364/2009/A
5.4.6.
Only Non-inert
C&D waste was disposed of in this reporting month. Details of the waste
flow table are summarized in Table 5.19.
Table 5.19 Details
of Waste Disposal for Contract no. HY/2009/19
Inert
C&D materials disposed |
NIL |
NIL |
N/A |
Inert
C&D materials recycled |
NIL |
630.954 |
N/A |
Non-inert
C&D materials disposed |
6.99 |
20.341 |
SENT Landfill |
Non-inert
C&D materials recycled |
0.09 |
0.09 |
N/A |
Chemical
waste disposed |
NIL |
0.1 |
N/A |
6.0.1.
The Event Action
Plan for construction noise, air qualities are presented in Appendix 6.1.
Contract
no. HY/2009/17 –Central – Wan Chai Bypass (CWB) at FEHD Whitfield Depot –
Advanced piling works under FEP-03/364/2009
6.1.1.
One
action level exceedance was recorded regarding one noise complaint regarding to noise were received on 20
December 2011.
6.1.2.
No limit level exceednace was recorded in the reporting month.
Contract
no. HY/2009/18 – Central – Wan Chai Bypass (CWB) – Central Interchange under
FEP-05/364/2009/A
6.1.3.
One non-project related limit level exceedance was recorded on 20 December
2011 during day time at M7e. Since traffic noise contributed in front of car
Contract no. HK/2009/01 – Wan Chai Development Phase II –
Central – Wan Chai Bypass at
6.1.4.
No exceednace was recorded in the reporting month.
Contract
no. HK/2009/02 – Wan Chai Development Phase II – Central – Wan Chai Bypass at
Wan Chai East (CWB Tunnel) under FEP-01/364/2009
6.1.5.
No action level and two limit level exceedances were recorded at M1a on 29
November and 6 December 2011 during restricted hour. Investigation
found that major traffic noise was contributed in the noise monitoring and
contractor complied with the requirement in valid CNP during restricted hours
noise monitoring.
Contract no. HY/2009/15 – Central-Wanchai Bypass – Tunnel (
6.1.6.
No exceednace was recorded in the reporting month.
Contract no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
6.1.7.
One
action level exceedance was recorded regarding one
noise complaint regarding to noise were received on 20 December 2011.
6.1.8.
No limit level exceednace was recorded in the reporting month.
Real Time Noise Monitoring
Contract no. HY/2009/17 –
Central – Wan Chai Bypass (CWB) at FEHD Whitfield Depot – Advanced piling works under FEP-03/364/2009
6.1.9.
No exceednace was recorded in the reporting month.
Contract no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
6.1.10.
No exceednace was recorded in the reporting month.
Contract
no. HY/2009/17 – Central – Wan Chai Bypass (CWB) at FEHD Whitfield Depot –
Advanced piling works under FEP-03/364/2009
6.2.1.
No exceedance was recorded in the reporting month.
Contract
no. HY/2009/18 – Central – Wan Chai Bypass (CWB) – Central Interchange under
FEP-05/364/2009/A
6.2.2.
No exceednace was recorded in the reporting month.
Contract
no. HK/2009/01 – Wan Chai Development Phase II – Central – Wan Chai Bypass at
6.2.3.
No exceednace was recorded in the reporting month.
Contract no. HK/2009/02 – Wan Chai Development Phase II – Central – Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
6.2.4.
No exceednace was recorded in the reporting month.
Contract no. HY/2009/15 – Central-Wanchai Bypass – Tunnel (
6.2.5.
No exceednace was recorded in the reporting month.
Contract
no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point Section) and
Island Eastern Corridor Link under FEP-07/364/2009/A
6.2.1
No exceednace was recorded in the reporting month.
6.3.1.
There was no
non-compliance from the site audits in the reporting period. The observations
and recommendations made in each individual site audit session were presented
in Section 8.
6.3.2.
No
project-related non-compliance from monitoring was recorded in the reporting
month.
7.0.1.
According to
Condition 3.4 of the EP-364/2009/A, this section addresses the relevant
cumulative construction impact due to the concurrent activities of the current
projects including the Central Reclamation Phase III (CRIII), Wan Chai
Development Phase II (WDII), Central-WanChai Bypass (CWB), Island Eastern
Corridor Link projects (IECL) and Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan Chai
East (CWB Tunnel).
7.0.2.
From the Monthly
EM&A report (November 2011) of Central Reclamation Phase III the key works
in December 2011 are as follows:
·
Type A
filling in FRAW and FRAE above +2.5mPD
·
General
filling works above +2.5mPD in IRAE
·
Surcharging
in FRAW and FRAE
·
Construction
of GPO boundary wall
·
Construction
of PLA boundary wall
·
Construction
of Promenade enhancement works
·
Construction
of buildings at PLA berth
·
Installation
of cooling mains discharge pipes in FRAE and FRAW
·
Backfilling
of CWB structure
·
Importation
of fill material
7.0.3.
According to the construction programme of Central Reclamation
Phase III, Wan Chai Development Phase II, Central-Wan Chai Bypass and Island
Eastern Corridor Link projects, the major construction activity under Central Reclamation
Phase III were general filling works in IRAE; Wan Chai Development Phase II was
marine works at HKCEC areas, cross-harbour Watermains, Fresh Watermains,
Cooling Watermains and Salt Watermains Installations, tunnel works at Wan Chai
East, seawall block construction, reclamation work and diaphragm wall
construction at TS4; Diaphragm wall construction at TS1 and TPCWAE TCBR1W. Advanced
piling works at FEHD Whitfield Depot, Central Interchange, and diaphragm wall
construction at North Point area. The major environmental impact was water
quality impact at
7.0.4.
The major environmental impacts generated from CRIII
advanced piling works at FEHD Whitfield Depot were undertaken and Diaphragm
wall construction at Central and tunnel works at Wan Chai East, IECL and
8.0.1.
During this
reporting month, weekly environmental site audits were conducted for Contracts
no. HY/2009/15, HY/2009/17, HY/2009/18, HY/2009/19, HK/2009/01 and HK/2009/02.
No non-conformance was identified during the site audits.
8.0.2.
Four site
inspections for Contract no. HY/2009/15 was carried out during this reporting
period. The results of these inspections and outcomes are summarized in Table
8.1.
Table 8.1 Summary
of Environmental Inspections for Contract no. HY/2009/15
Item |
Date |
Observations |
Action taken by Contractor |
Outcome |
111129_01 |
29-Nov-11 |
Silty
water was observed slightly leaking outside the silt curtain for the
protection of seawall collapsed. Investigation found that the seabed was
distributed by compressed air for the rectification works. The contractor
should review the silt curtain and deploy suitable silt curtain for the
operation. |
Review the silt curtain and deploy suitable silt curtain for the
operation |
Completion
as observed on 6-Dec-11 |
111129_02 |
29-Nov-11 |
Milky
water was discharged at the discharge point after treatment. The contractor
was reminded to review the efficiency of the system (TS1). |
Review the efficiency of the waste water treatment system |
Completion
as observed on 6-Dec-11 |
111206_01 |
6-Dec-11 |
Drip tray
shall be provided for chemical storage (Ex-TPCWA). |
Provide drip tray for chemical storage |
Completion
as observed on 13-Dec-11 |
111206_02 |
6-Dec-11 |
Packed
cement bags shall be covered by tarpaulin (Ex-TCPWA). |
covered packed cement bags by tarpaulin |
Completion
as observed on 13-Dec-11 |
111213_01 |
13-Dec-11 |
Oil
leakage from an oil drum was observed at TS1. The contractor was reminded to
provide drip tray and proper label. Moreover, the oil stains needed to be treated with proper
treatment. |
Provide
drip tray and proper label. Moreover, the oil needed to be treated with proper
treatment. |
Completion
as observed on 20-Dec-11 |
111220_01 |
20-Dec-11 |
Drip tray
shall be provided for chemical storage (TS1, ExTCPWA). |
Drip tray provided for chemical storage |
Completion
as observed on 29-Dec-11 |
111220_02 |
20-Dec-11 |
Floating
refuse shall be collected (TS1, TS4). |
Collect floating refuses |
Completion
as observed on 29-Dec-11 |
111220_03 |
20-Dec-11 |
Waste
water from site cleaning shall be collected and treated properly prior
discharge (Entrance of CWB PRE site office). |
Treat and collect the surface runoff outside site
boundary. |
Completion
as observed on 29-Dec-11 |
111220_04 |
20-Dec-11 |
Sloping
seawall shall be properly protected by geotextile (TS4). |
Protect the slopping seawall properly |
In progress |
8.0.3.
Four site
inspections for Contract no. HY/2009/18 was carried out during this reporting
period. The results of these inspections and outcomes are summarized in Table
8.2.
Table 8.2 Summary
of Environmental Inspections for Contract no. HY/2009/18
Item |
Date |
Observations |
Action taken by Contractor |
Outcome |
111201_01 |
1-Dec-11 |
Idle
stockpiles shall be covered by tarpaulin (C1, CR3). |
Cover idle stockpile by tarpaulin |
Completion
as observed on 8-Dec-11 |
111208_01 |
8-Dec-11 |
Contractor
was reminded to provide drip tray for any chemical containers. |
provide
drip tray for any chemical containers |
Completion
as observed on 22-Dec-11 |
111222_01 |
22-Dec-11 |
Surface
runoff outside the site boundary at |
Treat and collect the surface runoff outside site
boundary. |
Completion
as observed on 29-Dec-11 |
111222_02 |
22-Dec-11 |
Drip tray
shall be provided for chemical storage. ( |
provide
drip tray for any chemical containers |
Completion
as observed on 29-Dec-11 |
8.0.4.
Four site
inspections for Contract no. HY/2009/19 was carried out during this reporting
period. The results of these inspections
and outcomes are summarized in Table 8.3.
Table 8.3 Summary
of Environmental Inspections for Contract no. HY/2009/19
Item |
Date |
Observations |
Action taken by Contractor |
Outcome |
111130_01 |
30-Nov-11 |
The
contractor was reminded to repair the plants that were leaking oil during
operation as far as practicable. Otherwise, proper protections for the oil
spillage should be provided (temp. platform F4 in front of city garden). |
Provide protection for the oil leakage plants |
Completion
as observed on 7-Dec-11 |
111207_01 |
7-Dec-11 |
The silt
curtain at temporary works platform shall be improved. |
Improve the silt curtain for temporary works
platform |
Completion
as observed on 14-Dec-11 |
111214_01 |
14-Dec-11 |
The
contractor was reminded to review the wheel washing procedures at |
Review the wheel washing procedures at |
Completion
as observed on 19-Dec-11 |
8.0.5.
Four site
inspections for Contract no. HK/2009/01 was carried out during this reporting
period. The results of these inspections and outcomes are summarized in Table
8.4.
Table 8.4 Summary
of Environmental Inspections for Contract no. HK/2009/01
Item |
Date |
Observations |
Action taken by Contractor |
Outcome |
111130_01 |
30-Nov-11 |
Oil stain
on the bare ground at HKCEC3w shall be proper cleared up and disposed as
chemical waste. |
Proper cleared up and disposed the oil strain as chemical waste |
Completion
as observed on 7-DEC-11 |
111130_02 |
30-Nov-11 |
Sand bags
along the site access at north-bound up of HKCEC shall be enhanced to avoid
spillage of wastewater out of site boundary. |
Replace the new sandbags |
Completion
as observed on 7-DEC-11 |
111207_01 |
7-Dec-11 |
Excavator
located |
Repair the plant and drip tray |
Completion
as observed on 30-DEC-11 |
111207_02 |
7-Dec-11 |
The tress
at TST shall be regularly watered. |
Water the tree |
Completion
as observed on 14-DEC-11 |
111214_01 |
14-Dec-11 |
Oil
leakage from crawler crane was found at HKCEC1. Maintenance work for this
plant shall be provided. The contaminated soil on the base ground shall be
removed and disposed with proper procedure. |
Repair the plant and collect the contaminated
soil and disposed with proper procedure |
Completion
as observed on 23-DEC-11 |
111221_01 |
21-Dec-11 |
Contaminated
soil at HKCEC1 shall be removed and handled as chemical waste. |
Collect the contaminated soil and disposed with
proper procedure |
Completion
as observed on 30-DEC-11 |
111221_02 |
21-Dec-11 |
The edge
of soil screen at HKCEC1 shall be maintained and improved. |
maintained
and improved the edge of soil screen |
Completion
as observed on 30-DEC-11 |
111221_03 |
21-Dec-11 |
The
deployed silt curtain adjacent to VIP drop off area shall be improved. |
Improve the silt curtain |
Completion
as observed on 30-DEC-11 |
111221_04 |
21-Dec-11 |
The soil
found at the edge
of TST shall be trimmed-off. |
Trimmed-off the soil at the edge |
Completion
as observed on 30-DEC-11 |
8.0.6.
Four site
inspections for Contract no. HK/2009/02 was carried out during this reporting
period. The results of these inspections and outcomes are summarized in Table
8.5.
Table 8.5 Summary
of Environmental Inspections for Contract no. HK/2009/02
Item |
Date |
Observations |
Action taken by Contractor |
Outcome |
111201_01 |
1-Dec-11 |
Oil
leakage from an excavator was found at |
Provide
the maintenance work to the plant and remove contaminated soil as chemical
waste. |
Completion
as observed on 8-Dec-11 |
111201_02 |
1-Dec-11 |
Worn sandbags located at seafront near Sun Hung
Kei intakes shall be replaced. |
Replace the new sandbags |
Completion
as observed on 8-Dec-11 |
111201_03 |
1-Dec-11 |
Drip tray
shall be placed underneath the oil containers at ex-pet Garden. |
Provide drip tray for chemical storage |
Completion
as observed on 8-Dec-11 |
111201_04 |
1-Dec-11 |
Contractor
was reminded that no wastewater shall be leaking from the truck during
transportation. |
Ensure the soil is dry enough before transport |
Completion
as observed on 8-Dec-11 |
111208_01 |
8-Dec-11 |
Oil
leakage was found from the crawler crane at ex-Pet Garden. Plants maintenance
shall be provided be contaminated soil shall be handle as chemical waste with
proper procedure. |
Repair the plant and collect the contaminated
soil and disposed with proper procedure |
Completion
as observed on 15-Dec-11 |
111208_02 |
8-Dec-11 |
Ponding
water shall be avoided to accumulate at the site near western seawall. |
Review and maintain a proper site drain |
Completion
as observed on 15-Dec-11 |
111208_03 |
8-Dec-11 |
Floating
fine particle near western seawall shall be removed. |
Remove the fine particle |
Completion
as observed on 15-Dec-11 |
111215_01 |
15-Dec-11 |
Permanent
protective measures shall be provided for the oil leakage plants if the
leakages could not be prevented. (Ex |
Provide permanent protective measures to the oil
leakage plants |
Completion
as observed on 19-Dec-11 |
111215_02 |
15-Dec-11 |
C & D materials inside drip tray
shall be collected ( |
Collect the C&D materials. |
Completion
as observed on 19-Dec-11 |
111219_01 |
19-Dec-11 |
Maintenance
work shall be provided to the derrick barge (城堡3) to avoid dark smoke emission. |
Provide maintenance work to the derrick barge |
Completion
as observed on 29-Dec-11 |
111219_02 |
19-Dec-11 |
Oil drum
located at |
Provide drip tray for chemical storage |
Completion
as observed on 29-Dec-11 |
8.0.7.
Four site
inspections for Contract no. HY/2009/17 were carried out during this reporting
period. No observation was found in the reporting month.
9.0.1.
Two environmental complaints were received on 12
and 20 December 2011 in the reporting month.
9.0.2.
A visual impact complaint from hotline 1823 was
received by ET on 9 January 2012 (ICC Ref. No.: ICC#1-333037096 dated on 12
December 2011). The complaint, Mr Tsui reported that visual nuisance caused by
lighting in the construction site regarding HY/2009/18 during night time. A
joint inspection was conducted by Mr. Tsui and contractor on that night to see
whether there is any improvement.
9.0.3.
Due to safety reason, igniting enough lights should
not be avoided in construction site. However, the light sources were not
directed away from pointing to the sensitive receiver and results in visual
glare to the complaint
9.0.4.
Confirmed with the Resident Site Staff the
complainant was satisfied the new arrangement of the lights with contractor
after the joint inspection. No further complaint received after that.
9.0.5.
The second complaint was raised from the
complainant, Ms. Poon complained via hotline 1823 (Ref no.: 1-334683841)
regarding the construction air and noise nuisance generated that many trucks
carrying construction materials driving along Watson Road and Oil Street relevant
to the contractor no. HY/2009/17 and HY/2009/19 and possibly entering/leaving
the construction site near the Island Eastern Corridor during 0800 to 1900
hours on 20 December 2011.
9.0.6.
The dominant construction air and noise nuisances were
emitted from the trucks along
9.0.7.
Since The complainant cannot identify whether the
trucks were working under the CWB project or not, CWB RSS provided a contact
no. for any future enquiries regarding CWB project to the complainant and she
was satisfied on the arrangement and no further complaint was received after
that.
9.0.8.
The details of cumulative complaint
log and updated summary of complaints are presented in Appendix
9.1
9.0.9.
Cumulative
statistic on complaints and successful prosecutions are summarized in Table
9.1 and Table 9.2 respectively.
Table 9.1 Cumulative
Statistics on Complaints
Reporting
Period |
No. of
Complaints |
December 2011 |
2 |
Sep 10 to November
11 |
13 |
Total |
15 |
Table 9.2 Cumulative Statistics on Successful Prosecutions
Environmental
Parameters |
Cumulative
No. Brought Forward |
No. of
Successful Prosecutions this month (Offence Date) |
Cumulative
No. Project-to-Date |
Air |
- |
0 |
0 |
Noise |
- |
0 |
0 |
Water |
- |
0 |
0 |
Waste |
- |
0 |
0 |
Total |
- |
0 |
0 |
10.0.1. The EM&A programme was carried out in
accordance with the EM&A Manual requirements, minor alterations to the
programme proposed were made in response to changing circumstances.
10.0.2. The scheduled construction activities and the
recommended mitigation measures for the coming month are listed in Table
10.1. The construction programmes of individual contracts are provided
in Appendix 10.1.
Table 10.1 Summary of Key Construction Activities of Individual
Contract(s) to be commenced in Coming Reporting Month
Contract No. |
Key Construction Works |
Recommended Mitigation
Measures |
HY/2009/15 |
·
Diaphragm wall
construction at TS4 ·
ELS works at TS1 ·
Pumping test and ELS preparation
works at TPCWAE ·
Night time protection
works at CHT ·
Construction of
dewatering well at ·
Precautionary works at
Abutment A |
·
Watering any dust
generating activities ·
Checking all drip trays
frequently and clear any stagnant water and mud inside it. ·
Noise control measures
shall be provided during restricted hours. |
HY/2009/17 |
·
ELS works for basement
construction for pile cap construction. |
·
Noise barrier shall be
implemented; and ·
Watering any dust
generating activities |
HY/2009/18 |
·
Instrumentation
works for Manholes and Intake Culvert Survey ·
Excavation
of trial pit ·
Drainage
work at ·
Site
investigation and pre-drilling works at CR3 ·
Diaphragm
wall construction ·
Hoarding
erection ·
Roadworks
at CR3 ·
Grout
curtain ·
Sheet-piling ·
Tree
purning |
·
Noise barrier shall be
implemented; and ·
Noise level shall be
controlled by reducing piling rate and no. of plants working in parallel. ·
Dust control during dust
generating works |
HY2009/19 |
·
Remove
existing dolphin ·
Road
works at ·
Fabrication
of bored piling platform ·
Bored
piling ·
Ground
contamination assessment ·
Pre-drilling
works for bored pile and Diaphragm wall ·
D-wall
Construction ·
Sheet
piling for Box Culvert T ·
Construction
works for Box Culvert T ·
Marine
Piling |
·
Noise level shall be controlled
by reducing the operation rate. ·
Noise barrier shall be
deployed for dolphin pier removal. |
HK2009/01 |
·
Diaphragm
Wall construction works for both CWB within HKCEC 1 ·
Pre-drilling
works for CWB at Stage 2. ·
Pilling
works for CWB at Stage 2. ·
Excavation
and installation of shoring system for CWB top slab. |
·
Noise level shall be
controlled by reducing pilling rate. ·
Well maintain the
enclosures for grouting and bentonite mixing plants. |
HK/2009/02 |
·
Deep
excavation works below +1mPD for western tunnel portion and below +4mPD for
eastern tunnel portion. ·
Toe
grout, Shear pine, and Pumping test at WCR1 area. |
·
Noise level shall be
controlled by reducing pilling rate. ·
Well maintain the
enclosures for grouting and bentonite mixing plants. |
10.0.3. The construction works of Contract no. 04/HY/2006 –
Reconstruction of Bus Terminus near